As an important equipment of concrete production line. concrete mixing plant needs to work step by step. therefore. as a concrete mixing plant operator. you need to be familiar with the concrete mixing plant workflow steps.



Next. NFLG will tell you what are the steps of concrete mixing plant workflow?

1. After the mixer control system is powered on. it enters the human-computer dialogue operation interface.

2. The system will be initialized. including formula number. concrete. slump. production quantity. etc.

3. according to the weighing of each bin. measuring hopper detection. output material empty or material full signal. prompting the operator to determine whether to start the mixing control program

4. Start sand and stone belt motor to feed material to the measuring hopper

5. Open the butterfly valve of fly ash and cement tank

6. Start the screw conveyor motor to convey fly ash and cement to the measuring hopper

7. open the control valve of water bin and admixture pool to make water and admixture flow into the measuring hopper

8. measurement set requirements after opening the metering bucket door.

9. The ingredients enter the mixer which has been started to mix and blend. open the mixer door at the set time. and the concrete enters the mixer truck which has received the materials.



The machine has an order of switching. if there is improper operation. it will form a lot of trouble.

The order of the concrete mixing plant switch is very important. if the operation is not proper. will form the concrete mixing plant downtime. machine blockage and so on. the formation of machine repair. maintenance and protection.